#lfc anticipate that the Anfield Road stadium development will take 22-23 months to complete and to open in time for the start of the football season. So with work expected to commence next summer/autumn - approval pending - it will be open for the start of the 2023-24 season.
Of the (up to) 7,000 additional seats, (up to) 1,800 will be premium.
The proposal would see #lfc's overall "official" capacity increase to 61,015, split by:
Main Stand - 20,676
Sir Kenny Dalglish Stand - 11,348
The Kop - 13,024
Anfield Road Stand - 15,967
The proposal includes a covered fan zone within the expanded stand itself. #lfc
The "exploded" view of what the redeveloped Anfield Road stand would look like by level. #lfc